| 12 | |
| 13 | === From George Damm's test notes === |
| 14 | |
| 15 | There are actually 2 different test scenarios for checking things during a FPA takedown, 1) FPA on ground and 2) FPA on telescope. The differences are due to missing pieces of equipment. When the FPA is on the ground, both the BIB and the HPF ACQ cameras are not present, they are mounted on the assembly with the IHMP. |
| 16 | |
| 17 | The collision avoidance hall-effect sensors in the carriages of the Guider1 and 2 and WFS1 and 2 cannot be tested in an automated fashion since collision avoidance routines will keep them from getting close enough to each other. The carriages must be moved by hand while watching for the pertinent bits to be triggered. |
| 18 | |
| 19 | I will list what I have for a test procedure in a slightly different format, keeping like functionality together. |
| 20 | |
| 21 | 1) FPA on Telescope |
| 22 | |
| 23 | Taking images on all cameras will verify the functionality of the single board computers (if they are used) |
| 24 | |
| 25 | 1. Verify functioning images on Guider1, Guider2, WFS1, WFS2,ACQ Cam, PV Camera, CWFS Camera, BIB Camera, HPF ACQ camera |
| 26 | |
| 27 | 2. Verify functioning probes by moving them to Beginning of Range then to End of Range and then back again. Record carriage and probe arm motor current for post processing on Guider1, Guider2, WFS1, WFS2 |
| 28 | |
| 29 | 3. Verify PFIP Shutter motion |
| 30 | |
| 31 | 4. Move to all filter positions for Guider1, Guider2, ACQ Cam |
| 32 | |
| 33 | 5. Verify function of ACQ Cam focus |
| 34 | |
| 35 | 6. Move the three pneumatic actuators to both positions and verify, ACQ Cam fold mirror, PV/CWFS fold mirror, PV/CWFS selector |
| 36 | |
| 37 | 7. Check dither mechanism |
| 38 | |
| 39 | |
| 40 | 2) FPA on ground |
| 41 | |
| 42 | Same as above, remove test of BIB and HPF ACQ Cameras |
| 43 | |
| 44 | === From Jim Fowler's notes === |
| 45 | |
| 46 | Requirements for testing PFIP hardware in the FPA. |
| 47 | 10 Jun 2019 |
| 48 | |
| 49 | This is a hardware test only. Alignment tests will be done by the night staff |
| 50 | |
| 51 | Need to define the |
| 52 | |
| 53 | mechanism tested, |
| 54 | |
| 55 | commands sent, |
| 56 | |
| 57 | monitor point, |
| 58 | |
| 59 | success criteria, |
| 60 | |
| 61 | restrictions - prior tests, other mechanisms in particular locations/starting criteria |
| 62 | |
| 63 | ground/air test only? |
| 64 | |
| 65 | Tests |
| 66 | |
| 67 | verify communications with SBC systems |
| 68 | |
| 69 | move ACQ camera in/out |
| 70 | |
| 71 | expose ACQ cam |
| 72 | |
| 73 | operate filters |
| 74 | |
| 75 | for Guider1, Guider2, WFS1, WFS2 |
| 76 | |
| 77 | operate camera |
| 78 | |
| 79 | verify image |
| 80 | |
| 81 | operate filters |
| 82 | |
| 83 | verify sensors |
| 84 | |
| 85 | operate probes full range |
| 86 | |
| 87 | test limits |
| 88 | |
| 89 | measure currents |
| 90 | |
| 91 | check PV camera |
| 92 | |
| 93 | check CFWS camera |
| 94 | |
| 95 | move in/out |
| 96 | |
| 97 | check indicators |
| 98 | |
| 99 | take image |
| 100 | |
| 101 | check BIB camera |
| 102 | |
| 103 | take image |
| 104 | |
| 105 | operate shutter, visual check on the ground |
| 106 | |
| 107 | |
| 108 | Should we test for interactions between devices? |
| 109 | |
| 110 | |
| 111 | === Test Requirements === |