20160711 Commissioning Plan

Priorities for test are in the order listed in the plan below.


If you can open

Telescope functional tests

Purpose: Try a few basic tests to see if the telescope is operating in a normal fashion.

Procedure:

  • 8 position pointing test near center of track
  • Focus curve with GC1, GC2, and ACAM (can be done separately)
  • Check theta and phi position to get good image quality
  • Check DMI value at best GC1 or GC2 focus just after stacking.

Finding the center of the good UV chip on ACAM

Purpose: We need to find the center of the good UV chip on the ACAM. For science targets that need decent UV response.

Procedure:

  • Setup on a brightish star (14th) on LRS2B
  • Take a spectrum with LRS2
  • Look at instructions under Setup of LRS2 Observation for how to move around to in Telescope Offsets to get the correct position.
  • Offset the guider and telescope in a controlled way and take a new exposure.
  • Repeat until you have good centering on UV chip.
  • Insert the ACAM and record the star position in X and Y.
  • Document results on wiki and in e-mail.