= 20160711 Commissioning Plan = Priorities for test are in the order listed in the plan below. ------------- == If you can open == === Telescope functional tests === Purpose: Try a few basic tests to see if the telescope is operating in a normal fashion. Procedure: * 8 position pointing test near center of track * Focus curve with GC1, GC2, and ACAM (can be done separately) * Check theta and phi position to get good image quality * Check DMI value at best GC1 or GC2 focus just after stacking. === Finding the center of the good UV chip on ACAM === Purpose: We need to find the center of the good UV chip on the ACAM. For science targets that need decent UV response. Procedure: * Setup on a brightish star (14th) on LRS2B * Take a spectrum with LRS2 * Look at instructions under [wiki:HetProcedures/RA/lrs2#setup Setup of LRS2 Observation] for how to move around to in Telescope Offsets to get the correct position. * Offset the guider and telescope in a controlled way and take a new exposure. * Repeat until you have good centering on UV chip. * Insert the ACAM and record the star position in X and Y. * Document results on wiki and in e-mail.