  • NightOperations/Commissioning/Plans/20161202

    v1 v2  
    1  20161202 Commissioning Plan =
     1= 20161202 Commissioning Plan =
    22
    33
     
    1212
    1313== On-sky engineering: ==
     14
     15=== CWFS Focus Test ===
     16
     17 * Stack the primary mirror
     18 * Null out ANY tip-tilt offsets, best by re-starting TCS prior to this test
     19 * Setup on a geostationary satellite as close as possible to the center of the tracking sphere
     20 * insert and center CWFS
     21 * Set focus with CWFS
     22 * run CWFS with the loop active for 15 minutes, saving images and noting the start and stop time
    1423
    1524=== Run full tracks with bib camera+ to assess centroid drag ===