== Preparation for Pistoning == If pistoning is going to be done by the day staff the next day, there are several things the TO needs to do near the end of the night: · Perform a stack as late in the night as possible, ideally into twilight after science is done for the night. · Leave SAMS running in closed loop · Set the Dome AC to the temperature of the truss at the time of stack · Rotate the structure to 32 degrees (per the structure computer, not TCS) · Leave the Quincy Compressor running.